Billings City Council is set to adopt the new FY 2026-2030 Capital Improvement Plan (CIP) on Monday, Dec. 9, 2025.
The CIP is the plan for the city’s projects over the next five years, and the 2026 fiscal year begins in July 2025. Trail and bike lane projects in the FY 2026 plan include:
- Rimrock Road Improvements from Clearview Drive all the way to 62nd St. West
- Grand Avenue from 43rd Street West to 62nd Street West
- Monad Road from Daniels Street to Moore Lane
- Various pedestrian crossings
- Various trail repairs
The Stagecoach Trail does not show up in this CIP because the project was begun in fiscal year 2025, and engineering the trail has already begun! Engineering could take a year or more, so construction is likely to begin in 2027.
If these projects are important to you, we encourage you to contact City Council to let them know their relevance and the features these road projects need (trails? bike lanes? sidewalks?). You can contact City Council via emailing them here.